The management team has asked you to reschedule the project so it finishes two weeks earlier without spending more money. They haven't removed any requirements from the project. Which technique would you use to shorten the project?a. fast-track
b. assign more experienced people to tasks on the critical path
c. crash the schedule
d. cut scope