Both Projects A and B are acceptable as independent projects. However, the selection of either one of these projects eliminates the option of selecting the other project. Which one of the following terms best describes the relationship between Project A and Project B?
A. Dual return.
B. Conventional.
C. Crosswise.
D. Mutually exclusive.
E. Independent.

Respuesta :

Answer:

D. Mutually exclusive.

Explanation:

Mutually exclusive projects are projects that cannot occur together. If one project is chosen, the other has to be rejected.